首页/ 题库 / [单选题]Estimating schedule 的答案

Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.

单选题
2022-01-02 04:01
A、accuracy
B、approxination
C、specification
D、summary
查看答案

正确答案
B

试题解析

标签:
感兴趣题目
The process of( )schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.
The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.
Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.(74)
Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
Moving goods by rail often involves()costs, particularly when the shipper or receiver lack direct rail access.
相关题目

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

Involvement in community activities ______ an integral and inescapable part of senior managers' jobs.

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
International business covers all business activities that involve exchanges

The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
______is one of the techniques used for estimating activity durations.
( ) is one of the techniques used for estimating activity durations.
● (73) is one of the techniques used for estimating activity durations.(73)
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element
Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.
Learning is more effective when the learners are actively involved in the learning process.()
Learning is more effective when the learners are actively involved in the learning process.()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(2)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(1)处填()

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

广告位招租WX:84302438

免费的网站请分享给朋友吧