什么是双筋截面?在什么情况下才采用双筋截面?

问答题
2022-02-23 22:38
查看答案

正确答案
在单筋截面受压区配置受力钢筋后便构成双筋截面。在受压区配置钢筋,可协助混凝土承受压力,提高截面的受弯承载力;由于受压钢筋的存在,增加了截面的延性,有利于改善构件的抗震性能;此外,受压钢筋能减少受压区混凝土在荷载长期作用下产生的徐变,对减少构件在荷载长期作用下的挠度也是有利的。
双筋截面一般不经济,但下列情况可以采用:(1)弯矩较大,且截面高度受到限制,而采用单筋截面将引起超筋;(2)同一截面内受变号弯矩作用;(3)由于某种原因(延性、构造),受压区已配置;(4)为了提高构件抗震性能或减少结构在长期荷载下的变形。

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

A cabinet or space containing the controls or valves for the fixed firefighting system must be().
A cabinet or space containing the controls or valves for the fixed firefighting system must be().
什么叫ORS?如何配制?如何使用?
CASE OF DEATH OR SERIOUS INJURY TO A PERSON IN AN ACCIDENT OR SHIPPING DISASTER is().
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Damage to cargo caused by fumes or vapor from liquids,gases, or solids is known as().
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
Every deliberate act of wrongdoing by the master or any of the crew against the ship or cargo,without the authorization or privity of the Shipowner or his agent,is().
广告位招租WX:84302438

免费的网站请分享给朋友吧