首页/ 题库 / [单选题]

The project()is 的答案

The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

单选题
2022-01-01 12:41
A、work performance information
B、scope statement
C、changerequests
D、process analysis
查看答案

正确答案
B

试题解析

感兴趣题目
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
The schedule management plan is a component of the project management plan. The Schedule management plan maybe formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
(75)are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.
are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

( )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved. 空白(1)处应选择()
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
相关题目

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
Money is the key ________for me to decide whether I will take the job or not.

()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

A project life cycle is a collection of generally sequential project ( ) whose name and number are determined by the control needs of the organization or
● The completion and approval of one or more () characterizes a project phase.()A.deliverables B.products C.projects D.programs
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.

空白(1)处应选择()

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.


空白(2)处应选择()
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.
The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality), ( ), and cost

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. ( )is not a project selection method.
Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)
Symmetric, or private-key, encryption is based on a secret key that is shared by both communcating parties. The ( ) party uses the secret key as part of the mathematical operation to encrypt ( ) text to cipher text. The receiving party uses the same secret key to decrypt the cipher text to plain text. Asymmetric, or public-key, encryption uses two different keys for each user: one is a ( ) key known only to this one user; the other is a corresponding public key, which is accessible to anyone. The private and public keys are mathematically related by the encryption algorithm. One key ia used for encyption and the other for decryption, depending on the nature of the communication service being implemented. In addition, public key encryption technoligies allow digital ( ) to be placed on messages. A digital signature uses the sender&39;s private key to encrypt some portion of the message. When the message is received, the receiver uses the sender&39;s ( ) key tp decipher the digital signature to verify the sender&39;s identity.