All the following are root-cause analysis techniques used in quality management except( 74 ).

单选题
2022-01-05 16:13
A、fishbone diagrams
B、Ishikawa diagrams
C、system or process flowcharts
D、checklists
查看答案

正确答案
D

试题解析

标签:
相关题目
A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.
Many useful tools and techniques are used in developing schedule.( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
The plays known as “the Lawrence trilogy” are all the following EXCEPT ________.
Daniel Defoe’s works are all the following EXCEPT_____.
The following are all variations of idioms, EXCEPT ______.( )
The following are all denominal suffixes EXCEPT _________.( )
All of the following statements are true according to the passage EXCEPT that “_______”
All of the following acts are producing for the market EXCEPT ______( )
All of the following are part of the fire triangle EXCEPT().
All of the following are part of the fire triangle EXCEPT ().
All of the following are part of the fire triangle EXCEPT().
All of the following are part of the fire triangle except().
All of the following are true EXCEPT __.( )
All of the following are distress signals EXCEPT().
All of the following are engaged in fishing EXCEPT().
All of the following are recognized distress signals under the Navigation Rules EXCEPT().
all of the following tools and techniques are helpful to acurately confirming customers needs except ()

all of the following tools and techniques are helpful to acurately confirming customers needs except ()
 

he following are root-cause analysis techniques used in quality management except().
All the following are the objectives of ISM code except().
广告位招租WX:84302438

免费的网站请分享给朋友吧