连续梁桥的固定支座布置有何要求?

问答题
2022-01-18 17:54
查看答案

正确答案
一般在每一联设置一个固定支座,并宜将固定支座设置在靠近温度中心处,以使全梁的纵向变形分散在梁的两端,其余墩台上均设置活动支座。在设置固定支座的桥墩(台)上,一般采用一个固定支座,其余为横桥向的单向活动支座;在设置活动支座的所有桥墩台(台)上,一般沿设置固定支座的一侧,均布置顺桥向的单向活动支座,其余均布置双向活动支座。

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

对于多跨连续梁桥,可在纵向布置多个固定支座。(  )
对于多跨连续梁桥,可在纵向布置多个固定支座。(  )
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
桥梁固定支座的布置有何规定?
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
支座的作用是什么?连续梁桥的固定支座布置有何要求?
连续梁桥的固定支座布置有何要求?
对于多跨连续梁桥,可在纵向布置多个固定支座。
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
广告位招租WX:84302438

免费的网站请分享给朋友吧