首页/ 题库 / [单选题]()is one of the tool的答案

()is one of the tools and techniques of Sequence Activities.

单选题
2021-07-20 01:06
A、Decomposition
B、Fishbone Diagram
C、Precedence Diagramming Method
D、Expert Judgment
查看答案

正确答案
C

试题解析
下列()为活动排序的方法。
A.分解
B.鱼骨图
C.前导图法
D.专家判断

标签:
感兴趣题目
Which of the following is a characteristic of a sequence?()
One of the advantages in the use of a dry liner over a wet liner is()
The oil is drawn from a drain tank through (), one of a pair of pumps, into one of fine filters.
One hundred boys went on a school outing. Eighty-one percent of the boys lost a shoe, 82 percent of the boys lost a sock, 77 percent of the boys lost a handkerchief and 68 percent of the boys lost a hat.  What is the minimum percentage who lost all 4 items?
During the Ice Ages,man developed the use of tools,and this is a way of protecting himself against________.
( )is not the advantage of GERT (Graphical evaluation and review techniques)as compared with PERT (project evaluation and review techniques).
Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes.( ) are the techniques and tools in performing quality control.
① Statistical sampling
②Run chart Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes.( ) are the techniques and tools in performing quality control.
①Statistical sampling
②Run chart
③Control charts
④Critical Path Method
⑤Pareto chart
⑥Cause and effect diagrams
The magnitude of a moment is the product of the force and().
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().
(1) analysis emphasizes the drawing of pictorial system models to document and validate both existing and/or proposed systems.Ultimately, the system models become the(2) for designing and constructing an improved system. (3) is such a technique. The emphasis in this technique is process-centered.Systems analysts draw a series of process models called (4) . (5) is another such technique that integrates data and process concerns into constructs called objects.
Circles O and P intersect at exactly one point, as shown in the figure above. If the radius of circle O is 2 and the radius of circle P is 6, what is the circumference of any circle that has OP as a diameter?
A()is the intersection of the surface of a sphere and a plane passing through the center of the sphere.
相关题目
Who is the "father of English poetry" and one of the greatest narrative poets of English?
() is one of the tools and techniques.
()is one of the tools and techniques of Sequence Activities.
In a series of pamphlets Jonathan Swift denounced the cruel and unjust treatment of Ireland by the English government. One of the most famous is ____.
Which of the following features is NOT one of the design features of language? A
The most important shipping1 is the bill of 2 It is: firstly, a contract between the 3 and the shipping company; secondly, a receipt for the consignment; and thirdly, a document of 4 It not only contains a full 5 of the consignment-numbers and weights and marks of packages, but a lot of other information as well It lists the name of the shipper and the carrying vessel, the ports of 6 and7 The 8, the name of the consignee, and the 9of shipment, which is very important10 a contractual point of view
is a sequence of letters and digits, the first character mustbe a letter.
______ is a sequence of letters and digits, the first character must be a letter.
● (67) is a sequence of letters and digits,the first character must be a letter.
● (75) is a sequence of letters and digits,the first character mustbe a letter.
is a sequence of letters and digits, the first character must be a letter.
A vessel sounding a fog signal of one short,one prolonged,and one short blast is indicating that the vessel is().
( )is not the advantage of GERT (Graphical evaluation and review techniques)as compared with PERT (project evaluation and review techniques).
( )is not the advantage of GERT(graphical evaluation and review techniques) as compared with PERT(project evaluation and review techniques)
( ) is one of the tools and techniques of Sequence Activities
______is one of the techniques used for estimating activity durations.
( ) is one of the techniques used for estimating activity durations.
all of the following tools and techniques are helpful to acurately confirming customers needs except ()
● (73) is one of the techniques used for estimating activity durations.(73)
A sequence of any number of characters enclosed in the double queotes“”is called a character ______.
广告位招租WX:84302438

免费的网站请分享给朋友吧