All Of followings should be done by the project manager during project control except().

单选题
2022-01-03 03:12
A、Determine that a change has occurred
B、Ensure thata change is agreed
C、Make sure all changes are approved by management
D、Manage changes as they occur
查看答案

正确答案
C

试题解析
下列中,( )不是项目经理在项目控制过程组要完成的工作。 
A、确定变更已经发生 
B、确保变更被同意 
C、确保所有变更均被管理人员批准 
D、变更发生时对其进行管理 

标签:
感兴趣题目
The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the(27)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the ( ) of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
All of the following can be determined by use of a stabilogauge except().
SEARCHABLE NOTICES TO MARINERS can be searched by all the following options except().
10 Which of the following costs should be included in valuing inventories of finished goods held by a manufacturing
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
相关题目
The dilemmas created by the use of internet may be about all of the following aspects,except__________.
(1).   Which of the following is NOT done by satellites according to the passage?(本题2.0分)
Which of the following is NOT done by satellites according to the passage?
All of the following can be determined by use of a stabilogauge EXCEPT().
Digital data can be produced by all of the following expect ().
The term CFR should be followed by _____. 选项
Which of the following item should be covered in the major achievements
The Repairer shall be relieved of all obligations under these terms and conditions caused by such all following matters except().
If the ordered spare parts have been modified by manufacturer, which of the following should be pay attention to?()
After repair, the voyage trial of the M-E should be done ()
If the meter needle of the oxygen indicator cannot be set to zero,what should be done? ()
All Of followings should be done by the project manager during project control except().
Before engaging the turning gear and turning the diesel engine, which of the following operation should be done except ()
Before engaging the turning gear and turning the diesel engine, which of the following operation should be done except______.
The bilge system has been performing well; however, the aft starboard engine room bilgewell suddenly fails to be pumped outWhich of the following should be done first to determine the cause?()
A critical path for a project is the series of activities that determine( ) by which the project can be complete
Refrigerant entering the compressor of a refrigeration system should be in which of the following conditions?()
Which of the following steps should normally be taken first by those who have boarded a liferaft in an emergency situation?()
The project maintains a current and approved set of requirements over the life of the project by doing the following:
•( )all changes to the requirements
• Maintaining the relationships among the requirements, the project plans, and the work products
● The project maintains a current and approved set of requirements ovethe life of the project by doing the following:· (73) all changes to the requirements· Maintaining the relationships among the requirements, the project plansand the work products· ……(73)
广告位招租WX:84302438

免费的网站请分享给朋友吧