首页/ 题库 / [单选题]Project manager beli的答案

Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).

单选题
2022-01-03 11:23
A、change the scope baseline
B、contact the customer to determine if the change adds value
C、call a meeting of the change control board
D、change the project’s objectives
查看答案

正确答案
C

试题解析
项目经理相信调整范围能为客户增加收益,项目经理应该(73)。A:改变范围基线、B:联系客户确定变更是否增加收益、C:召开变更控制委员会会议、D:改变项目目标。

标签:
感兴趣题目
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.(71)
Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
Project ( ) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
相关题目

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

The key benefit of ( )is that it provides guidance and direction on how the project costs will be managed throughout the project.
Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ).
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .
Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.
● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).(75)
Risk management allows the project manager and the project team not to( ).
Risk management allows the project manager and the project team not to (71).
● Risk management allows the project manager and the project team not to(71).(71)
A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should( ). A.Tell the customer that he will not address any problems
●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).(71)

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the(27)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the ( ) of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management processes include all the activities of the ( )that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
Project Quality Management processes include all the activities of the(71)that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
广告位招租WX:84302438

免费的网站请分享给朋友吧