某独立土方工程,招标文件中估计工程量为200万m3,合同中规定:土方工程单价为8元/m3,当实际工程量超过估计工程量15%时,调整单价,单价调为6元/m3。工程结束时实际完成土方工程量为250万m3,则土方工程款为( )万元。
A、<p><span style="font-family: \'Microsoft YaHei\'; font-size: 13px; ">1960</span></p>
B、<p><span style="font-family: \'Microsoft YaHei\'; font-size: 13px; ">1600</span></p>
C、<p><span style="font-family: \'Microsoft YaHei\'; font-size: 13px; ">1200</span></p>
D、<p><span style="font-family: \'Microsoft YaHei\'; font-size: 13px; ">1900</span></p>
A、<p><span style="font-family: 'Microsoft YaHei'; font-size: 13px; ">1960</span></p>
B、<p><span style="font-family: 'Microsoft YaHei'; font-size: 13px; ">1600</span></p>
C、<p><span style="font-family: 'Microsoft YaHei'; font-size: 13px; ">1200</span></p>
D、<p><span style="font-family: 'Microsoft YaHei'; font-size: 13px; ">1900</span></p>