Given the estimated decrease in personal profit, what action you should take(46).
A、Invoice for the full $1,000,000 based on the contract.
B、Add tasks to improve the outcome and increase the actual project cost.
C、Inform. the end-user that you can add features to the project in order to use the entire budget.
D、Communicate the projected financial outcome to the project sponsor.
查看答案
正确答案
试题解析
解析:你管理一个项目,项目的估算成本是100万,项目发起人批准了这一额度。你的挣值计算表明项目将准时完工并低于20万美元。根据这一计算,你的个人利润将减少2000美元。考虑到个人利润的降低,你将把项目的财务结果传给项目发起人。