绩效衡量基线为()。

单选题
2022-03-12 19:47
A、计划价值
B、挣值
C、实际成本
D、计划完成工作的实际成本
查看答案

正确答案
A

试题解析
PV是绩效衡量基线或者最初预计的项目成本。PV,EV和AC被用来确定EAC以及成本和时间表变量。项目执行过程中任何时间点落后于时间表的情况都可能通过这些数据得到确定。

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

当系统显示出错信息:Bad command or file name时,应从()方面进行检查。
OR的流行病学含义为()。
ORS液配制后的张力为()
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
已知A=40;B=30;C=100;D=50,逻辑“与”运算符为and,“或”运算符为or,“非”运算符为not。计算表达式(A>B+20)or(B+60<>
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
管理(或非浮动)价格Administered(or inflexible) prices
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
绩效衡量基线为()
绩效衡量基线为()。
绩效衡量基线为()。
“绩效管理”系统的组成除了绩效的衡量与绩效信息反馈外,还包括()。
广告位招租WX:84302438

免费的网站请分享给朋友吧