首页/ 题库 / [单选题]The()technique invol的答案

The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

单选题
2022-06-29 15:08
A、costaggregation
B、reserve analysis
C、parametricestimating
D、funding limit reconciliation
查看答案

正确答案
A

试题解析
可以注意到该题的关键词为"mathematical model"和"predict total project cost",再划分语句结构"The()technique(主语)involves(谓语)using project characteristics in a mathematical model to predict total project cost",易理解语句含义为"什么技术使用数学模型预测项目的总成本"。观察四个选项,ABD也可能应用数学模型,也可能只是简单的数字规定,但选项C 一定会应用数学模型,所以应该选择parametric estimating。

标签: CMS专题
感兴趣题目
(75)are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.
are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion, they may also exert influence over the project and its results.
( )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved. 空白(1)处应选择()
The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
The(7)technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
相关题目

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
Many useful tools and techniques are used in developing schedule.( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
The( )technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.
The(72)technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.

 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.

空白(1)处应选择()

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.


空白(2)处应选择()
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. ( )is not a project selection method.
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)
广告位招租WX:84302438

免费的网站请分享给朋友吧