Cost of qunlity is ( )

单选题
2022-01-02 04:01
A、primarily coused by poor workmanship of workers who are building or manufacturing the produce
B、associated with non-conformence to specifications and requirements
C、used to determine whether a quality management program is suitable for a given project
D、negligible for most large projects
查看答案

正确答案
B

试题解析
质量成本与非一致性的规格、需求有关。质量成本PMBOK定义:质量成本包括在产品生命周期中为预防不符合要求、为评价产品或服务是否符合要求,以及因未达到要求返工,而发生的所有成本。

标签:
感兴趣题目
Which one of the following repair will cost the least cost?()
______ they to cut down the cost of advertising, the cost of production ______ significantly fall.
If 7 apples cost x dollars, how much do 70 apples cost, in terms of x?
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(2)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(1)处填()
The transmission of messages respecting the dangers specified is free()cost to the ships concerned.
The transmission of messages respecting the dangers specified is free()cost to the ships concerned.
You are working on the cost budget for one project. Which of the following is true()
One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()
If the bandwidth of an OSPF interface is 64, what would be the calculated cost of the link?()
A vessel has been damaged by fire. The survey shows the cost of repairs will exceed the value of the repaired vessel. This is an example of a(n)().
相关题目

 One big         of formal education is the high cost. 

_______________is the original cost of an asset less any accumulated depreciation
Which one of the following repair will cost the least cost?()
”Cost of quality ” is a project management concept that includes cost of ( ).
“Cost of quality”is a project management concept that includes cost of( 73)
Cost of qunlity is ( )
Cost of qunlity is (73)
The cost performance index(CPI) is the ratio of earned value to () and can be used to estimate the projected cost of completing the project.
The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
Pipeline is low cost and reliable. Is it true? ()
Pipeline is able to deliver the products based on the advantages of low rate of loss and damage, minimal climatic effects and reduced labor cost. Do you agree? ()
Christopher bought 4 cans of soup for a total of $3.36,which included sales tax of $0.16. At the same per-can cost, what is the cost before the sales tax is added for 6 cans of the same soup?
Cost of pipeline is very different of underground conditions. Is it right? ()
______ is the sending and receiving of the messages by computer. It is a fast, low-cost way of communicating worldwide.
is the sending and receiving of the messages by computer. It is a fast, low-cost way of communicating worldwidE..
is the sending and receiving of the message by computer. It is a fast, low-cost way of communicating worldwide。
The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality), ( ), and cost
A complaint of unseaworthiness by a majority of crew members to the American Consul is found to be justified after a survey is completed. Who must pay the cost of the survey?()
Software Engineering Economy is an effective part of software engineering.Which of the following content is the research content of software engineering economy?Ⅰ.Estimation of software development costⅡ.Earn & Cost analysis of software developmentⅢ.Adjustment of software development progress
广告位招租WX:84302438

免费的网站请分享给朋友吧