首页/ 题库 / [问答题]简述钢结构疲劳含义,列出其主要影响因素并的答案

简述钢结构疲劳含义,列出其主要影响因素并作简要分析?

问答题
2022-01-02 06:05
查看答案

正确答案

(1)钢结构构件和其连接在很多次重复加载和卸载作用下,在其强度还低于钢材抗拉强度甚至低于钢材屈服点的情况下突然断裂,称之为疲劳破坏。
(2)影响因素有:应力集中大小;循环应力大小;应力变化的循环次数;残余应力情况。


试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

检索式“转基因食品 or 安全”的基本含义是( )
检索式“禽流感 or 预防”的基本含义是( )
检索式“转基因食品 or 安全”不包括的含义是( )
OR的流行病学含义为()。
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
简述钢结构疲劳含义,列出其主要影响因素并作简要分析?
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
简述布尔算符(OR)的作用。
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
广告位招租WX:84302438

免费的网站请分享给朋友吧