首页/ 题库 / [单选题]钢筋混凝土预制打入桩平卧叠浇制作下层混凝的答案

钢筋混凝土预制打入桩平卧叠浇制作下层混凝土达到()设计强度方可浇注上层。

单选题
2022-01-02 15:48
A、25%
B、30%
C、40%
D、50%
查看答案

正确答案
B

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

预制桩制作时,上层桩或邻桩的浇筑必须载下层桩的混凝土达到设计强度的( )方可进行:
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
预制桩制作时,上层桩或邻桩的浇筑必须载下层桩的混凝土达到设计强度的()方可进行:
钢筋混凝土预制打入桩平卧叠浇制作下层混凝土达到()设计强度方可浇注上层。
钢筋混凝土预制桩采用平卧叠浇,下层混凝土达到()设计强度方可浇注上层
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
卧叠浇预制混凝土桩,浇注上层混凝土时下层混凝土应达到()
打入预制钢筋砼桩的电焊接桩工程是按()计算。
采用叠浇法制作钢筋混凝土预制桩的规定有()
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
Every deliberate act of wrongdoing by the master or any of the crew against the ship or cargo,without the authorization or privity of the Shipowner or his agent,is().
广告位招租WX:84302438

免费的网站请分享给朋友吧