● The completion and approval of one or more () characterizes a project phase.()A.deliverables B.products C.projects D.programs

单选题
2022-01-03 04:07
A、deliverables
B、products
C、projects
D、programs
查看答案

正确答案
A

试题解析
每个项目阶段都以一个或数个可交付成果的完成为标志。

标签:
感兴趣题目
from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
( ) from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.
According to Annex Ⅳ of comminuted and disinfected sewage using an approved system can be discharged when the ship is more than away from the nearest land()
A c() sentence contains two or more clauses, one of which is incorporated in the other.
Jitter is an unwanted variation of one or more characteristics of a periodic signal in electronics and telecommunications and()refers to call issues that cause variations in timing or time of arrival.
(75)are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.
are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.
are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion, they may also exert influence over the project and its results.
( )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
The records of ship security training, drills and exercises shall be kept in the working language or languages of the shipIf the language or languages used are not(), a translation into one of these languages shall be included.
相关题目

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

The ways in which words follow one another and are related to one another is called the syntagmatic dimension of language, the dimension of “chaining” or “sequencing”.()
In Charles Dickens’early novels, he attacks one or more specific social evils, _____is a good example of describing the dehumanizing workhouse system and the dark, criminal underworld life.
Choose the one that best completes each of the following statements. The two main islands of the British Isles are .
It is obvious that the future of the Internet is to________ more and more areas of the world,and that e-commerce and e-entertainment are going to go for more and more markets
● The completion and approval of one or more () characterizes a project phase.()A.deliverables B.products C.projects D.programs
With one or more cylinders out of operation, the engine speed must be reduced because()
The auxiliary steering gear must be capable of being brought speedily into operation and be able to put the rudder over from 15 degrees on one side to 15 degrees on the other side in no more than () with the ship at its deepest service draught and running ahead at the greater of one half of the maximum service speed or ().
One of the greatest features of a home ______ is the ability to share one Internet connection simultaneously over two or more computers.
For one or two types of engine, the piston and rod can be withdrawn downwards from the cylinder into the crankcase and then out through the ().
For one or two types of engine,the piston and rod can be withdrawn downwards from the cylinder into the crankcase and then out through ().
One of the greatest features of a home(74)is the ability to share one Internet connection simultaneously over two or more computers.
When the renewal verification is completed more than three months before the expiry date of the existing Document of Compliance or Safety Management Certificate, the new Document of Compliance or the new Safety Management Certificate should be valid from the date of () for a period not exceeding five years.
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
One of the biggest worries for governments is that the longer people live,the more likelihood there is for diseases and for disability(残疾 ).
The ways in which words follow one another and are related to one another is called the syntagmatic dimension of language, the dimension of “chaining” or “sequencing”.()
The ways in which words follow one another and are related to one another is called the syntagmatic dimension of language, the dimension of “chaining” or “sequencing”.()
For the duties assigned in the muster list, one person may do more than one work and one work may be done by more than one person.()

() from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

广告位招租WX:84302438

免费的网站请分享给朋友吧