梁桥桥台水平地震作用是如何考虑的?

问答题
2022-01-03 09:32
查看答案

正确答案

作用于桥梁桥台上的水平地震作用包括台身水平地震力、台背主动土压力以及上部结构对桥台顶面处产生的水平地震力。E1地震作用抗震设计阶段,应考虑地震时动水压力和主动土压力的影响,在E2地震作用抗震设计阶段,一般不考虑。


试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

OR指令的作用是:(  )  
 OR指令的作用是:( )
OR指令的作用是:( )
OR指令的作用是:(  )
什么叫ORS?如何配制?如何使用?
()m高度以上的高层建筑在荷载组合时,应同时考虑重力荷载、水平地震作用及风荷载。
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
梁桥桥台水平地震作用是如何考虑的?
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
简述布尔算符(OR)的作用。
梁桥桥台水平地震作用是如何考虑的? 
广告位招租WX:84302438

免费的网站请分享给朋友吧