对不含砾或含少量砾的粘性土料,以干重度为设计指标,按击实试验最大干重度乘以压实系数确定,并用压实度来控制;对坝体的砂、砂砾、石料等同样要求进行填筑压实,但非粘性土的压实特性与含水量关系不大,主要与粒径级配和压实功能有密切关系,常用相对紧密度控制。
粘性土的控制指标:对Ⅰ、Ⅱ级坝和高坝,填土的压实度应不低于0.97—0.99;对Ⅲ级及其以下的坝(高坝除外)P应不低于0.95—0.97。
非粘性土的控制指标:要求达到密实状态,相对紧密度不低于0.70—0.75。在地震情况下,浸润线以上不低于0. 7,浸润线以下按设计烈度大小而定,一般不低于0.75—0.85。当非粘性土中粗粒含量小于50%时,应保证细料(小于5mm的颗粒)的相对密实度满足以上要求。


试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

A cabinet or space containing the controls or valves for the fixed firefighting system must be().
A cabinet or space containing the controls or valves for the fixed firefighting system must be().
CASE OF DEATH OR SERIOUS INJURY TO A PERSON IN AN ACCIDENT OR SHIPPING DISASTER is().
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
粘性土料和非粘性土料填筑标准用什么指标控制?如何确定这些指标?
土石坝各组成部分对土料的要求怎样?粘性土料和非粘性填筑标准用什么指标控制?
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
管理(或非浮动)价格Administered(or inflexible) prices
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
广告位招租WX:84302438

免费的网站请分享给朋友吧