首页/ 题库 / [单选题]某工程双代号时标网络计划中,工作H有三项的答案

某工程双代号时标网络计划中,工作H有三项紧后工作,其工作总时差分别为4、6和7周,工作H的自由时差为2周,则工作H的总时差是()周。

单选题
2021-07-17 20:39
A、<p>4</p>
B、<p>6</p>
C、<p>7</p>
D、<p>9</p>
查看答案

正确答案
B

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

某社会经济现象在一定时期内平均每期增长的绝对数量是(  )。[2010年中级真题]
某工程双代号时标网络计划如下图所示,以下选项中,正确的结论有(  )。[本题缺图,仅供参考]
Rent, economic(or pure economic rent) 经济租或纯经济租
在某单位工程双代号时标网络计划中()。
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
某工程双代号时标网络计划如下图所示(单位:周),。。。,工程E可以利用的机动时间是()
某分部工程双代号时标网络计划如下图所示,该计划所提供的正确信息有(  )。
某工程双代号时标网络图如下图所示,下列选项中正确的有(   )。
双代号时标网络计划是指带有时间坐标的双代号网络计划。
在某单位工程双代号时标网络计划中,( )。
双代号时标网络计划中,波形线表示工作的(  )。[2010年真题]
广告位招租WX:84302438

免费的网站请分享给朋友吧