首页/ 题库 / [单选题]During planning you 的答案

During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()

单选题
2022-03-02 18:02
A、The team did not create the estimate and estimating tales too long using that method
B、The team did not create the estimate and a network diagram was not used
C、The estimate is too long and should be created by management
D、The project estimate should be the same as the customer's required completion date
查看答案

正确答案
B

试题解析

标签:
感兴趣题目

 ______ you prepare cross training plans, you need to consider both the company benefits and the employee benefits.

During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()
During the voyage he encountered boisterous winds and heavy weather during which time the vessel()heavily and to such an extent that at times it was necessary to change course.
Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( )
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(2)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(1)处填()
Shall we sit up here on the grass or down there near the water?()
Shall we sit up here on the grass or down there near the water? ()
If you register both the VIEW qualification course and the Forum at the same time, you will save ______.
The more time you spend on the Internet, the less time you are with your family and friends.
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
相关题目

 ______ you prepare cross training plans, you need to consider both the company benefits and the employee benefits.

The love and support of his family ______ him during his difficult times.( )
The love and support of his family ______ him during his difficult times.
They all the details of the plan time and again to make sure that the project went smoothly.
15. The love and support of his family ______ him during his difficult times.
10. The love and support of his family ______ him during his difficult times.
Don’t lose time in carrying out your plan. Otherwise you will lose the chance.( )
For days at a time the driver’s life ___________ sitting, eating and sleeping
You can sit here in your spare time.You can sit here when you’re ____.
Do you think we can get there on time-Yes,the truck doesnt break down
Shall we sit up here on the grass or down there near the water? ()
●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
Your tank vessel is fully loaded, and you find that she is down slightly by the head. To adjust the trim, you may().
You are proceeding down a channel and lose the engine(s).You must use the anchors to stop the ship.Which statement is true().
The Crown Court sits at()centers and is presided over by High Court Judges,full-time Circuit Judges and part-time Recorders.

You are planning the creation of a new multitenant container database (CDB) and want to store the ROOT and SEED container data files in separate directories.
You plan to create the database using SQL statements.
Which three techniques can you use to achieve this?()

Examine the parameter for your database instance:
You generated the execution plan for the following query in the plan table and noticed that the nested loop join was done. After actual execution of the query, you notice that the hash join was done in the execution plan:
Identify the reason why the optimizer chose different execution plans.()

The engine may lose power or slow down during running, when this occurs, the first cause possible may be hot bearings and () of the pistons in the cylinders.
The time required to incline from bow down to stern down and return to bow down again is called().
广告位招租WX:84302438

免费的网站请分享给朋友吧