建设工程合同索赔是指在建设工程合同实施过程中,当事人一方因对方违约或非自身原因而遭到损失时,向对方提出的赔偿要求。  
建设工程合同索赔的主要原因有:  
⑴合同风险分担不均;  
⑵施工条件变化;  
⑶工程变更;  
⑷工期拖延;  
⑸业主违约;  
⑹合同缺陷;  
⑺国家法令的变更;  
⑻其它。  
建设工程合同索赔的依据有:  
⑴合同和合同文件;  
⑵施工文件和有关资料;  
⑶前期索赔文件;  
  ⑷法律与法规。

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

A cabinet or space containing the controls or valves for the fixed firefighting system must be().
A cabinet or space containing the controls or valves for the fixed firefighting system must be().
在国际货物买卖合同中载明:FOB liner terms or FOB stowed & trimmed,则表示()。
CASE OF DEATH OR SERIOUS INJURY TO A PERSON IN AN ACCIDENT OR SHIPPING DISASTER is().
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Damage to cargo caused by fumes or vapor from liquids,gases, or solids is known as().
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
Every deliberate act of wrongdoing by the master or any of the crew against the ship or cargo,without the authorization or privity of the Shipowner or his agent,is().
广告位招租WX:84302438

免费的网站请分享给朋友吧