说明在建筑工程施工公开招标中,资格预审的程序。

问答题
2022-04-02 18:22
查看答案

正确答案

试题解析

1招标人确定招标方式;到建设行政主管部门办理备案手续。

2)编制招标文件。

3)发布招标公告或发出投标邀请通知书。

4)向投标人发出投标资格预审通知书,对投标单位进行资格预审。

5)向投标人发出招标文件。采用投标人资格预审方式的,招标人只向资格预审合格的投标人发出招标文件

6)组织必要的答疑、现场勘察、解答投标人提出的问题,编写答疑文件或补充投标文件等。

7)接受投标书。

8)组织开标、评标、决标。

9)招标人自确定中标人之日起十五日内建设行政主管部门提交招标投标情况的书面报告。

10)向投标人发出中标或未中标通知书。

11)与中标人订立书面委托监理合同。


相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

Goods are carried by several        of transport--on road or rail, by sea or air.

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

A cabinet or space containing the controls or valves for the fixed firefighting system must be().
A cabinet or space containing the controls or valves for the fixed firefighting system must be().
CASE OF DEATH OR SERIOUS INJURY TO A PERSON IN AN ACCIDENT OR SHIPPING DISASTER is().
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Damage to cargo caused by fumes or vapor from liquids,gases, or solids is known as().
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
Every deliberate act of wrongdoing by the master or any of the crew against the ship or cargo,without the authorization or privity of the Shipowner or his agent,is().
广告位招租WX:84302438

免费的网站请分享给朋友吧