Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resource

单选题
2022-06-14 03:43
A、work breakdown structure
B、baseline
C、software requirements specification
D、plan
查看答案

正确答案
A

试题解析
制定项目进度计划之前,制定计划者需要()、各任务的工作量估计以及可能得到的资源列表
A、分解结构
B、基线
C、软件需求描述
D、计划

标签:
感兴趣题目
The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.
You want to schedule a job to rebuild all indexes on the SALES table after the completion of a bulk load operation. The bulk load operation must also be a scheduled job that executes as soon as the first file that contains data arrives on the system. How would you create these jobs?()
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
Which of the following tools can be used to schedule a backup operation that is to be run every Sunday evening?()
You need to create a schedule that will run a job on the second Friday of each month. What should the repeat interval of the schedule be set to?()
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
The(7)technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
was developed to make clear the interdependence between project tasks before those tasks are scheduled.
相关题目
This project must be completed ___as scheduled.
The( )technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.
The(72)technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.
The decision about such a big project can not be made each member of the board agrees.

 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

The cost performance index(CPI) is the ratio of earned value to () and can be used to estimate the projected cost of completing the project.
Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.
A schedule is commonly used in project planning and project portfolio management. () on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.
A critical path for a project is the series of activities that determine( ) by which the project can be complete
The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used bythe roject management team to( ).
● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .(73)
The project life-cycle can be described as (72).
● The project life-cycle can be described as(72).(72)
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
How can a Job with EXEC as Internal Status be stopped in the Job Scheduling Console?()
Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resource
The schedule management plan is a component of the project management plan The
The schedule management plan is a component of the project management plan. The Schedule management plan maybe formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
广告位招租WX:84302438

免费的网站请分享给朋友吧