首页/ 题库 / [单选题]The earned value tec的答案

The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).

单选题
2022-03-15 23:13
A、the project is ahead of its planned schedule
B、less work was completed than was planned
C、the cost overrun for work completed
D、the cost under-run of performance to date
查看答案

正确答案
B

试题解析
挣值分析技术是一种综合了范围、成本、进度指标的常用绩效测量方法。它帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着()。
A.进度超前B.进度滞后 C成本超支 D成本结余
根据《系统集成项目管理工程师教程》(全国计算机专业技术资格考试办公室组编)第9.5.3小节的内容可知,SPI值小于1表示实际进度落后于计划进度。
因此,正确答案应选B。

标签:
感兴趣题目
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
WebSphere Commerce Accelerator will be used to create a product. The product has 6 variations determined by attributes Size, which has three values and Color, which has two values. What is the PREFERRED method to create the product and its SKUs using the Product Management tool?()
Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)
Which of the following drug is used to treat the alcohol withdrawal symptom commonly
"crolling" is a technique most commonly associated with ______.
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
()is a technique used for illumination behind the liquid crystal display that makes LCDs easier to read.
A common technique used to prevent the unauthorized network devices from sending trafficacross a network is port()
Sequential circuit is a common logic device whose output values, at a given instant, depend upon its input values and the internal state at that instant, and whose internal state depends upon the(66)preceding input values and the preceding internal state. A sequential circuit can assume a finite number of internal states and may therefore be regarded, from an abstract(67), as a finite(68).Combinational circuit is another logic device whose output values, at any given instant, depend upon the input values at that instant. A combinational circuit is a(69)of a sequential circuit whose internal state is not taken(70).
相关题目
A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
Many useful tools and techniques are used in developing schedule.( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
Earned value analysis is an example of()。
______is one of the techniques used for estimating activity durations.
( ) is one of the techniques used for estimating activity durations.
● (73) is one of the techniques used for estimating activity durations.(73)
Which of the following techniques is used to extract the /usr/tmp directory from a mksysb backup?()
The cost performance index(CPI) is the ratio of earned value to () and can be used to estimate the projected cost of completing the project.
A common means of connecting shots of anchor chain in the field is to use a().
The most common type of containment device for spilled oil on the water is the use of ().
The most common instrument used to measure diesel engine exhaust pressure is the ()
The display screen is the most common (72) device used to show you what the computer is doing.
______ the most versatile of the common metals, lead was widely valued and used in ancient times.
A(73)is a value that never changes, for example: the value of Pi(approximately 3.14).
Which one of the following is the most commonly used layer 2 network device?()
The star formation is most commonly used and requires() on the alternator.
A common class of wire rope used for mooring is the 6x19 class. What does the 6 represent?()
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index(CPI=EV/AC) value less than 1.0, it means that ( )
广告位招租WX:84302438

免费的网站请分享给朋友吧