首页/ 题库 / [单选题]( )estimating is a t的答案

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

单选题
2022-06-29 15:07
A、Parametric
B、Analogous
C、Three-point
D、Expert judgment
查看答案

正确答案
B

试题解析

标签:
感兴趣题目
Which statement about an estimated position is TRUE?()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(2)处填()
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(1)处填()
The Beaufort scale is used to estimate the().
Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resource
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
The Estimate Activity Resource process is closely coordinated with the(73) process.
The Estimate Activity Resource process is closely coordinated with the (73)process.(73)
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
Over a third of the population was estimated()(无法获得) to the health service.
相关题目

A budget is an estimation of the _______ and _______ over a specified future period of time.

It is estimated that much of a teenager's time is spent______ with friends.
At a rough estimate, Nigeria is __________ Great Britain.
Over a third of the population was estimated to have no _____ to the health service.
It is estimated that much of a teenager\'s time is spent______ with friends.
A fairly accurate estimation of a ship’s position can be calculated by a technique known as().
A fairly accurate estimation of a ship’s position can be calculated by a technique known as().
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
This year’s output of the factory is estimated ( )10000 tons.
______is one of the techniques used for estimating activity durations.
( ) is one of the techniques used for estimating activity durations.
● (73) is one of the techniques used for estimating activity durations.(73)
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
How can you estimate the position of a tropical storm’s center?()
Any Works completion date quoted by the Repairer is an estimate only and the Repairer shall not be()liable for any failure to complete the Works by that date.
At a rough estimate,Nigeria is()Great Britain.
Preliminary estimation puts the figure at around $110 billion,()the $160 billion the President is struggling to get through the Congress.
A position that is obtained by applying estimated current and wind to your vessel’s course and speed is a(n) ().
A position that is obtained by applying estimated current and wind to your vessel’s course and speed is a(n)().
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()
广告位招租WX:84302438

免费的网站请分享给朋友吧