首页/ 题库 / [单选题]某建筑工程合同造价为780万元,工程预付的答案

某建筑工程合同造价为780万元,工程预付备料款额度为工程合同造价的20%,工程保留金为工程合同造价的5%,则该工程的预付备料款和保留金分别为( )万元。

单选题
2021-09-01 20:51
A、150,30
B、145,45
C、130,40
D、156,39
查看答案

正确答案
D

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

A cabinet or space containing the controls or valves for the fixed firefighting system must be().
某建筑工程合同造价为780万元,工程预付备料款额度为工程合同造价的20%,工程保留金为工程合同造价的5%,则该工程的预付备料款和保留金分别为( )万元。
Logistic回归系数与优势比OR的关系为()。
世界卫生组织推荐使用的口服补液盐(ORS)溶液的张力为()。
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
已知A=40;B=30;C=100;D=50,逻辑“与”运算符为and,“或”运算符为or,“非”运算符为not。计算表达式(A>B+20)or(B+60<>
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
Every deliberate act of wrongdoing by the master or any of the crew against the ship or cargo,without the authorization or privity of the Shipowner or his agent,is().
广告位招租WX:84302438

免费的网站请分享给朋友吧