某工程计划中M工作的持续时间为3天,总时差为6天,自由时差为4天。如果M工作实际进度拖延9天,则会影响工程计划工期( )。

单选题
2021-09-06 21:21
A、3天
B、4天
C、5天
D、10天
查看答案

正确答案
A

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

A cabinet or space containing the controls or valves for the fixed firefighting system must be().
Logistic回归系数与优势比OR的关系为()。
(多选、25分) 在某工程网络计划中,已知M工作的自由时差为3天,如果在执行中M工作持续时间拖了2天,则此工作M(  )。
某工程计划中M工作的持续时间为3天,总时差为6天,自由时差为4天。如果M工作实际进度拖延9天,则会影响工程计划工期( )。
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
管理(或非浮动)价格Administered(or inflexible) prices
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()

在某工程网络计划中,已知M工作的自由时差为3天,如果在执行中M工作持续时间拖了2天,则此工作M(  )。

()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
广告位招租WX:84302438

免费的网站请分享给朋友吧