首页/ 题库 / [单选题]单代号网络计划的自由时差等于( )。的答案

单代号网络计划的自由时差等于( )。

单选题
2021-09-06 21:22
A、本工作与紧前工作时间间隔的最小值
B、本工作与紧后工作时间间隔的最小值
C、本工作与紧前工作时间间隔的最大值
D、本工作与紧后工作时间间隔的最大值
查看答案

正确答案
B

试题解析

感兴趣题目
相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

单代号网络计划的自由时差等于( )。
单代号网络计划与双代号网络计划相比,具有的特点是()。
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
双代号时标网络计划中以( )表示工作的自由时差。
常用工程网络计划类型包括:双代号网络计划、单代号网络计划、双代号时标网络计划、单代号搭接网络计划。
常见的施工项目网络计划有双代号网络计划、单代号网络计划、时标网络计划、搭接网络计划。
单代号网络计划与双代号网络计划相比,具有()的特点。
单代号网络计划与双代号网络计划相比,具有的特点是( )。
已知某工程双代号网络计划的计划工期等于计算工期,且工作M的完成节点为关键节点,则该工作自由时差等于总时差。
单代号网络计划的自由时差等于()。
双代号网络计划的自由时差等于()
广告位招租WX:84302438

免费的网站请分享给朋友吧