首页/ 题库 / [单选题]流水段不变的条件下,流水步距大小直接影响的答案

流水段不变的条件下,流水步距大小直接影响( )。

单选题
2021-09-06 21:22
A、流水节拍的大小
B、资源投入量
C、施工过程多少
D、工期长短
查看答案

正确答案
D

试题解析

感兴趣题目
(), or drum is used for hauling in or letting out the wires or ropes which will fasten the ship to the shore.
A salvor may be()the whole or part of the payment due under Salvage Convention to the extent that the salvage operations have become necessary or more difficult because of fault or neglect on his part or if the salvor has been guilty of fraud or other dishonest conduct.
The () is used for hauling in or letting out the wires or ropes.
Vessels must be()valid certificate of nationality or certificated of registry or license.
When loading or discharging dry mud or cement,crew members should use goggles and().
Effects which are dutiable or subject to prohibitions or restrictions should be declared in ().
逻辑运算符(AND、NOT、OR)的运算顺序是AND→OR→NOT。
基础工程划分4个施工过程(基槽开挖、垫层、混凝土浇筑、回填土)在5个施工流水段组织固定节拍流水施工,流水节拍为3d,要求混凝土浇筑3d后才能进行回填土,其中基槽开挖与垫层施工搭接1d,该工程的流水施工工期为()d。
基础工程划分4个施工过程(基槽开挖、垫层、混凝土浇筑、回填土)在5个施工流水段组织固定节拍流水施工,流水节拍为3日,要求混凝土浇筑3日后才能进行回填土施工,其中基槽开挖与垫层施工搭接1日,该工程的流水施工工期为()日。
某工程划分4个流水段,由两个施工队进行等节奏流水施工,流水节拍4天,则总工期为()。
某工程划分为4个流水段,共4层,组织两个施工队进行等节奏流水施工,流水节拍为4天,其工期为( )。
逻辑运算符(AND、NOT、OR)的运算顺序是AND→OR→NOT。
相关题目
基础工程划分4个施工过程(基槽开挖、垫层、混凝土浇筑、回填土)在5个施工流水段组织固定节拍流水施工,流水节拍为3d,要求混凝土浇筑3d后才能进行回填土施工,其中基槽开挖与垫层施工搭接1d,该工程的流水施工工期为()d。
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

某工程划分为4个流水段,组织2个施工队进行等节拍流水施工,流水节拍为4天,其工期是()天
多层建筑物组织流水施工,为使各班组能连续施工,则流水段数m与施工过程数n的关系为( )。
流水段不变的条件下,流水步距大小直接影响( )。
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
组织流水施工时,流水段的划分应与主要施工过程相协调,且满足()。
若设定的条件表达式为“<60 Or>100”表示( )。
若设定的条件表达式为“<60 Or>100”,则表示( )。
组织流水施工时,流水段的划分应与主要施工过程相协调,且满足( )。
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
Every deliberate act of wrongdoing by the master or any of the crew against the ship or cargo,without the authorization or privity of the Shipowner or his agent,is().
广告位招租WX:84302438

免费的网站请分享给朋友吧