同一个施工过程依次连续、均衡地施工,而不同施工过程呈平行进行状态的施工方式称( )。

单选题
2021-09-06 21:22
A、依次施工
B、平行施工
C、流水施工
D、连续施工
查看答案

正确答案
C

试题解析

相关题目
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing

A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.

同一个施工过程依次连续、均衡地施工,而不同施工过程呈平行进行状态的施工方式称( )。
在应用ORS液的过程中,错误的做法是()
在应用ORS液的过程中,错误的作法是()
在应用ORS液的过程中,错误的是()
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
在工程项目施工过程中,可以采用以下三种组织方式:依次施工、平行施工与流水施工。
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
Shutdown price(or point,or rule) 停业价格(或停业点、停业原则)
翻译:With Average or With Particular Average(WA or WPA)()
将各工程对象划分为若干施工过程,每个施工过程的施工班组从第一个工程对象开始,连续地、均衡地、有节奏地一个接一个,直至完成最后一个工程对象的施工任务,这种组织施工的方法称为()
()shall be liable for loss of and damage to the Vessel and/or goods arising or resulting from inaccuracies in stating the description,quantity,weight,measurement or contents.
广告位招租WX:84302438

免费的网站请分享给朋友吧