Project schedule的答案

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

单选题
2021-12-31 19:28
A、activity duration estimating, schedule developing, activity resource estimating
B、activity resource estimating, activity duration estimating, schedule development
C、schedule developing, activity resource estimating, activity duration estimating
D、activity resource estimating, schedule developing, activity duration estimating
查看答案

正确答案
B

试题解析

感兴趣题目
The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
Demand curve(or demand schedule) 需求曲线(或需求表)
(75)are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.
are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion, they may also exert influence over the project and its results.

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
相关题目

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

Difficult _____ the project was, I managed to finish it on schedule.
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
A schedule is commonly used in project planning and project portfolio management. () on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.
The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality), ( ), and cost

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. ( )is not a project selection method.
● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .(73)
Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)
Difficult _____ the project was, I managed to finish it on schedule.
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
Team selection is not just a function of finding someone whos a technical or administrative expert. What will a project sponsor leading a high visibility project look for in a project manager?()
The schedule management plan is a component of the project management plan The
The schedule management plan is a component of the project management plan. The Schedule management plan maybe formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
广告位招租WX:84302438

免费的网站请分享给朋友吧