Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.

单选题
2021-12-31 19:28
A、activity duration estimating, schedule developing, activity resource estimating
B、.activity resource estimating, activity duration estimating, schedule development
C、schedule developing, activity resource estimating, activity duration estimating
D、activity resource estimating, schedule developing, activity duration estimating
查看答案

正确答案
B

试题解析
项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule development,所以选B。

标签:
感兴趣题目
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
The word “photographically” is made up of 5 morphemes.
The word “photographically” is made up of 4 morphemes.
The schedule management plan is a component of the project management plan The
The schedule management plan is a component of the project management plan. The Schedule management plan maybe formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
( )is a project management technique for measuring project performance and progress.It has the ability to combine measurements of the project management triangle: scope , time and costs.
( )is a project management technique for measuring project performance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.
相关题目
Classification of vowels is made up of the following EXCEPT()。
The word “photographically” is made up of 5 morphemes.
A six-strand composite rope made up of alternate fiber and wire strands around a fiber core is called().

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
”Cost of quality ” is a project management concept that includes cost of ( ).
“Cost of quality”is a project management concept that includes cost of( 73)
A schedule is commonly used in project planning and project portfolio management. () on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.
In project management and systems engineering,()is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.
Project Quality Management must address the management of the project and the(27)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the ( ) of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality), ( ), and cost
The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used bythe roject management team to( ).
● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .(73)
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index(CPI=EV/AC) value less than 1.0, it means that ( )
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
广告位招租WX:84302438

免费的网站请分享给朋友吧