The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understandin is reached on the meaning of the requirements. The result of this analysis and dialog is an ( )set of requirements.
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
空白(1)处填()(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
空白(2)处填()(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
空白(3)处填()The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.