● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)(75)

单选题
2022-03-12 19:13
A、Project Scope Statement
B、Project Management Plan
C、Forecasts
D、Project Charter
查看答案

正确答案
B

试题解析
试题(75)分析  项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到    (75) 。  A.项目范围说明书                    B.项目管理计划   C.项目预测                          D.项目章程参考答案  (75)B

标签:
感兴趣题目
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).
The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a ( )
● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)(75)
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
The schedule management plan is a component of the project management plan The
The schedule management plan is a component of the project management plan. The Schedule management plan maybe formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
( )is a project management technique for measuring project performance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.
The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()
相关题目

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

The inputs of developing project management plan do not include ( ).

The inputs of developing project management plan do not include()

The inputs of developing project management plan do not include (72) .
● The inputs of developing project management plan do not include (72).(72)
Risk management allows the project manager and the project team not to( ).
Risk management allows the project manager and the project team not to (71).
The quality management plan should describe how the project management team will implement its quality(73).
●The quality management plan should describe how the project management team will implement its quality (73).

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the(27)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the ( ) of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.
The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements.

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
广告位招租WX:84302438

免费的网站请分享给朋友吧