首页/ 题库 / [单选题]The process of( )sc的答案

The process of( )schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

单选题
2022-06-14 03:42
A、estimating
B、defining
C、planning
D、.sequencing
查看答案

正确答案
A

试题解析
估算活动历时的过程会用到活动工作范围、所需资源类型、估计的资源数量以及建立在资源可用性上的资源日历等信息。

标签:
感兴趣题目
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.
The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.
Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.(74)
Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
You are using the backup scheduler in Enterprise Manager (EM) to schedule a backup of your database. Which type of script does the backup scheduler generate?()
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
相关题目
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
______is one of the techniques used for estimating activity durations.
( ) is one of the techniques used for estimating activity durations.
● (73) is one of the techniques used for estimating activity durations.(73)

(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

空白(1)处填()

(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

空白(2)处填()

(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

空白(3)处填()
Define Activities is the process of identifying the specific actions to be performed to produce the ( ).
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).(71)
Which of the following methods is used to increase the number of processes sharing the CPU?
●Which of the following methods is used to increase the number of processes sharing the CPU? (72) .
The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used bythe roject management team to( ).
● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .(73)

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

The process of( )schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
广告位招租WX:84302438

免费的网站请分享给朋友吧