The(15)provides the project manager with the authority to apply organizational resources to project activities.

单选题
2022-06-28 18:45
A、project management plan
B、contract
C、project human resource plan
D、project charter
查看答案

正确答案
D

试题解析
解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

标签:
感兴趣题目

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

Project Quality Management must address the management of the project and the(27)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the ( ) of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
The()provides the project manager with the authority to apply organizational resources to project activities.
The()provides the project manager with the authority to apply organizational resources to project activities.
An advantage with one of the education projects is that the managers
The(15)provides the project manager with the authority to apply organizational resources to project activities.
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
相关题目
The(  )provides the project manager with the authority to apply organizational resources to project activities。

The()provides the project manager with the authority to apply organizational resources to project activities.

The key benefit of ( )is that it provides guidance and direction on how the project costs will be managed throughout the project.
Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ).
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .
Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.
● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).(75)
Risk management allows the project manager and the project team not to( ).
Risk management allows the project manager and the project team not to (71).
● Risk management allows the project manager and the project team not to(71).(71)
●A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should (72) .(72)
A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should( ). A.Tell the customer that he will not address any problems
The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The projectmanager maintains this link through( ).
●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).(71)
The ( ) provides the project manager with the authority to apply organizational resources to project activities。

The()provides the project manager with the authority to apply organizational resources to project activities.

To ensure the project team provide the functionlity the customer expects in a new prece of software, the project manager ask the customer for sing-off on the design crieria.There documents are( ).
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.
广告位招租WX:84302438

免费的网站请分享给朋友吧